High-altitude hydroelectric megaproject in Austria

Construction is underway on the K眉htai 2 hydroelectric power plant in Austria, with about 200 machines and 620 workers from more than ten countries working in tandem to build a more than 200-million-kwh facility.

K眉htai 2 hydroelectric plant project(Image: Volvo CE) Aerial view of the K眉htai 2 hydroelectric plant construction project in the Austrian Alps. (Image: Volvo CE)

Nestled 2,000m above sea-level in the municipality of Silz in the Tyrolean Stubai Alps, K眉htai 2 is a major development by the Austrian utility company Tiroler Wasserkraft (TW).

The K眉htai power plant will be built underground in a rock cavern that is designed for pumped storage operation and will be powered by two Flensi turbines generating up to 190MW of electricity.

Construction involves several tasks, both under and above ground. Underground includes the construction of an 8km network of supply access tunnels (cleared via drilling and blasting), as well as a 25.5km bypass tunnel with a diameter of 4.2m, which will be excavated by an 800-tonne tunnel boring machine (TBM).

Peter Wetzlinger of Swietelsky (Image: Volvo CE) Peter Wetzlinger (Image: Volvo CE)

鈥淭his is a gravity tunnel in which water is drawn in via six water intakes at a rate of up to 13.5m3 per second,鈥� said Peter Wetzlinger, project manager of Swietelsky 鈥� one of three construction management firms working the site (alongside J盲ger Bau and Bodner).

The bypass pipeline will open new catchment areas in the central and eastern 脰ztal valley and the rear section of the Stubaital valley and deliver water into the new K眉htai reservoir. The reservoir will have a storage volume of 31-million-m3 and will fill up two-and-a-half times a year, typically in spring and autumn.

Wetzlinger noted, 鈥淚n order to fill the reservoir, a 7-million-m3 dam, with a crest length of 500m and height of 106m, is being constructed.鈥�

In total, TW has invested approximately US$1 billion on the scheme to expand its existing system of power plants in the Sellrain-Silz region. 

Construction is expected to finish in 2026.

A peek at the machine works on the K眉htai 2 project
Volvo CE machines work the K眉htai 2 site (Image: Volvo CE) Volvo CE machines work the K眉htai 2 site in Austria. (Image: Volvo CE)

Sweden-based construction equipment manufacturer Volvo Construction Equipment (Volvo CE) has about 60 machines on site. The company said a brand-new Volvo EC950F is the flagship of the project excavator fleet.

The OEM added that its largest crawler excavator (a 90-tonne unit) is the first of its kind in Austria, with a second EC950F set to join the K眉htai 2 build soon.

鈥淭wenty-six Volvo articulated haulers, varying in size from the A25 to the A60 鈥� the largest articulated hauler on the market 鈥� perform the real backbone of the work on the site,鈥� said Volvo CE. 鈥淔ourteen A25 and A30 haulers alone are used for underground work and blasting, transporting material away.鈥�

Wetzlinger explained further some of the daily machine processes.

鈥淲e optimise the cross-sections so that the loading cycles with the Volvo L120, L150 and L180 wheel loader fit the A25 and A30 perfectly,鈥� he said. 

Larger hauler models were selected for earthworks due to improved off-highway capabilities. 鈥淲e needed articulated haulers because the rigid haulers can鈥檛 get everywhere, especially in certain areas of the quarry,鈥� added Wetzlinger. 鈥淎nd we can鈥檛 create highways. We need all terrain and all-wheel drive vehicles.鈥�

Each week 30-40 articulated haulers transport about 25 tonnes of bentonite each, which is mixed with a core material before delivery around the site.

Strabag trials fully autonomous asphalt paving Austria-based construction group Strabag has successfully tested new autonomous asphalt paving technology

Wetzlinger said, 鈥淒ue to the one-way operation, the routes are getting longer, so we are changing the machine fleet and getting more A60 haulers and another large EC950F excavator to help ensure we install the material on time.鈥�

He continued, 鈥淎ll material extracted from the underground area is recycled, with loose rock installed in the dam. In addition, we have to blast 2.2-million-m3 of rock 鈥� that鈥檚 around 50鈥�60,000m3 a week. We鈥檙e using [45 tonnes] of explosives per week and around 16,000l of diesel per day.鈥�

Fuel-savings at high-altitude for Volvo CE excavator
Volvo machines at the K眉htai 2 site (Image: Volvo CE) A fleet of Volvo CE machines at the K眉htai 2 site in Austria. (Image: Volvo CE)

Fuel usage has been slightly lower than an average site closer to sea level, as machines typically consume less fuel in high-altitude settings.

The Volvo EC950F, in particular, was operating around 50-55l of diesel daily.

鈥淲e didn鈥檛 believe it at the start, and thought the machine would consume more,鈥� says Wetzlinger. 鈥淏ut [the dealer鈥檚] predictions proved correct.鈥�

必赢体育

STAY CONNECTED

Receive the information you need when you need it through our world-leading magazines, newsletters and daily briefings.

CONNECT WITH THE TEAM
Andy Brown Editor, Editorial, UK - Wadhurst Tel: +44 (0) 1892 786224 E-mail: [email protected]
Neil Gerrard Senior Editor, Editorial, UK - Wadhurst Tel: +44 (0) 7355 092 771 E-mail: [email protected]
Catrin Jones Editor, Editorial, UK 鈥� Wadhurst Tel: +44 (0) 791 2298 133 E-mail: [email protected]
Eleanor Shefford Brand Manager Tel: +44 (0) 1892 786 236 E-mail: [email protected]